2007•Tiedao gongcheng xuebaoRequires access

Construction Technology of Large-section Collapsible Loess Tunnel

Wang Xiao-zhou, Wang Qing-lin, Lei Li

Open publisher page 1 citations

Abstract

Research purposes:Based on the construction of three large-section collapsible loess tunnels, Tongluochuan Tunnel,Gaoqiao Tunnel and Fenghuangling Tunnel,this paper analyzes and summarizes the CRD construction method of grade V large-section collapsible loess and proper process,distance between the stages,personnel,arrangement of facilities and equipments.Reference index of deformation stability-controlling was expounded by analyzing the relationship between ground settlement,vault settlement,horizontal shrink and excavation process,loess water content,rainfall and deformation rule. Research results:It ensures the practical progress index and time of every process circulation.From the experience and practice of construction,deformation-controlling measures are summarized and some problems about design and construction technology are submitted to be further probed and researched.

About this research paper

What this paper is about

Research purposes:Based on the construction of three large-section collapsible loess tunnels, Tongluochuan Tunnel,Gaoqiao Tunnel and Fenghuangling Tunnel,this paper analyzes and summarizes the CRD construction method of grade V large-section collapsible loess and proper process,distance between the stages,personnel,arrangement of facilities and equipments.Reference index of deformation stability-controlling was expounded by analyzing the relationship between ground settlement,vault settlement,horizontal shrink and excavation process,loess water content,rainfall and deformation rule. Research results:It ensures the practical progress index and time of every process circulation.From the experience and practice of construction,deformation-controlling measures are summarized and some problems about design and construction technology are submitted to be further probed and researched.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Research purposes:Based on the construction of three large-section collapsible loess tunnels, Tongluochuan Tunnel,Gaoqiao Tunnel and Fenghuangling Tunnel,this paper analyzes and summarizes the CRD construction method of grade V large-section collapsible loess and proper process,distance between the stages,personnel,arrangement of facilities and equipments.Reference index of deformation stability-controlling was expounded by analyzing the relationship between ground settlement,vault settlement,horizontal shrink and excavation process,loess water content,rainfall and deformation rule. Research results:It ensures the practical progress index and time of every process circulation.From the experience and practice of construction,deformation-controlling measures are summarized and some problems about design and construction technology are submitted to be further probed and researched.

Key concepts: Loess, Section (typography), Settlement (finance), Excavation, Geotechnical engineering, Engineering, Deformation (meteorology), Tunnel construction