Analysis on flow field in nearby waterways after Tiaozini reclamation construction in Jiangsu Province

Yong Zhou

Open publisher page 0 citations

Abstract

In order to predict the impact of Tiaozini reclamation construction on the marine environment,we established a two-dimensional tidal current mathematical model using Mike 21 software.The comparative analysis on changes of flow field and tidal flux in the main watercourse(Xiyang,Tiaoyugang and Waiwangjiacao) nearby Tiaozini sandbank before and after implementation of the reclamation project was conducted.The results showed that after the reclamation,the flow velocity in three waterways decreased during the flooding and ebbing tides,in which,the flow velocity in Xiyang waterway changed the most;the lateral flow was discovered in front of the reclamation dam,and the north and south flow trended to convergence and divergence in the east side of the dam.The tidal flux in Xiyang and Tiaoyugang waterways decreased obviously as a result of influence from the project.The dynamic environment in the east side of dam changes obviously,which may cause terrain erosion and deposition variation.

About this research paper

What this paper is about

In order to predict the impact of Tiaozini reclamation construction on the marine environment,we established a two-dimensional tidal current mathematical model using Mike 21 software.The comparative analysis on changes of flow field and tidal flux in the main watercourse(Xiyang,Tiaoyugang and Waiwangjiacao) nearby Tiaozini sandbank before and after implementation of the reclamation project was conducted.The results showed that after the reclamation,the flow velocity in three waterways decreased during the flooding and ebbing tides,in which,the flow velocity in Xiyang waterway changed the most;the lateral flow was discovered in front of the reclamation dam,and the north and south flow trended to convergence and divergence in the east side of the dam.The tidal flux in Xiyang and Tiaoyugang waterways decreased obviously as a result of influence from the project.The dynamic environment in the east side of dam changes obviously,which may cause terrain erosion and deposition variation.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In order to predict the impact of Tiaozini reclamation construction on the marine environment,we established a two-dimensional tidal current mathematical model using Mike 21 software.The comparative analysis on changes of flow field and tidal flux in the main watercourse(Xiyang,Tiaoyugang and Waiwangjiacao) nearby Tiaozini sandbank before and after implementation of the reclamation project was conducted.The results showed that after the reclamation,the flow velocity in three waterways decreased during the flooding and ebbing tides,in which,the flow velocity in Xiyang waterway changed the most;the lateral flow was discovered in front of the reclamation dam,and the north and south flow trended to convergence and divergence in the east side of the dam.The tidal flux in Xiyang and Tiaoyugang waterways decreased obviously as a result of influence from the project.The dynamic environment in the east side of dam changes obviously,which may cause terrain erosion and deposition variation.

Key concepts: Land reclamation, Hydrology (agriculture), Environmental science, Flow (mathematics), Terrain, Erosion, Flow velocity, Deposition (geology)

Related papers

Back to paper searchBrowse research topicsOriginal source
Analysis on flow field in nearby waterways after Tiaozini reclamation construction in Jiangsu Province — Research Paper | ScholarLens