2011•Zhejiang Electric PowerRequires access

Optimization Design of Installing Low Temperature Economizer for 200 MW Unit

Cheng Hui

Open publisher page 0 citations

Abstract

In order to solve the overtemperature problem of the boiler exhaust gas for the 200 MW units in a power plant,this paper presents the technical solution of installing low temperature economizer system through the optimization design of every key link.The low-temperature feedwater in the re-heating system is used to absorb the residual heat of the boiler exhaust gas.The exhaust gas temperature is lowered greatly without affecting the combustion of boiler.The potential problems in the system operation are predicted and analyzed,and the analysis of the design,structure parameters and thermal economy of low temperature economizer is presented.And it can serve as a reference for the retrofit of the power plants of the same type.

About this research paper

What this paper is about

In order to solve the overtemperature problem of the boiler exhaust gas for the 200 MW units in a power plant,this paper presents the technical solution of installing low temperature economizer system through the optimization design of every key link.The low-temperature feedwater in the re-heating system is used to absorb the residual heat of the boiler exhaust gas.The exhaust gas temperature is lowered greatly without affecting the combustion of boiler.The potential problems in the system operation are predicted and analyzed,and the analysis of the design,structure parameters and thermal economy of low temperature economizer is presented.And it can serve as a reference for the retrofit of the power plants of the same type.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In order to solve the overtemperature problem of the boiler exhaust gas for the 200 MW units in a power plant,this paper presents the technical solution of installing low temperature economizer system through the optimization design of every key link.The low-temperature feedwater in the re-heating system is used to absorb the residual heat of the boiler exhaust gas.The exhaust gas temperature is lowered greatly without affecting the combustion of boiler.The potential problems in the system operation are predicted and analyzed,and the analysis of the design,structure parameters and thermal economy of low temperature economizer is presented.And it can serve as a reference for the retrofit of the power plants of the same type.

Key concepts: Economizer, Boiler feedwater, Boiler (water heating), Exhaust gas, Power station, Installation, Combustion, Waste management

Related papers

Back to paper searchBrowse research topicsOriginal source
Optimization Design of Installing Low Temperature Economizer for 200 MW Unit — Research Paper | ScholarLens