A Study on the Rule of the New Critical Path in Condition of Critical Activity Being Crashed in CPM Network

Gang Zhong

Open publisher page 1 citations

Abstract

The rule of the new critical path,while the critical activity is crashed in CPM network,is discussed. Firstly,the paper proposes the Total Float Theorem and the Characteristic Path Theorem,on the basis of which the Substituting Critical Path Theorem is concluded.It shows that the new critical path,while a critical activity is discontinued, is surely the characteristic path passing through the activity which has minimum total float in all activities paralleling the discontinued critical activity.Finally,the paper presents a method and an example of finding the new critical path when critical activity is crashed.

About this research paper

What this paper is about

The rule of the new critical path,while the critical activity is crashed in CPM network,is discussed. Firstly,the paper proposes the Total Float Theorem and the Characteristic Path Theorem,on the basis of which the Substituting Critical Path Theorem is concluded.It shows that the new critical path,while a critical activity is discontinued, is surely the characteristic path passing through the activity which has minimum total float in all activities paralleling the discontinued critical activity.Finally,the paper presents a method and an example of finding the new critical path when critical activity is crashed.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The rule of the new critical path,while the critical activity is crashed in CPM network,is discussed. Firstly,the paper proposes the Total Float Theorem and the Characteristic Path Theorem,on the basis of which the Substituting Critical Path Theorem is concluded.It shows that the new critical path,while a critical activity is discontinued, is surely the characteristic path passing through the activity which has minimum total float in all activities paralleling the discontinued critical activity.Finally,the paper presents a method and an example of finding the new critical path when critical activity is crashed.

Key concepts: Critical path method, Float (project management), Path (computing), Mathematics, Computer science, Mathematical optimization, Economics, Management

Related papers

Back to paper searchBrowse research topicsOriginal source
A Study on the Rule of the New Critical Path in Condition of Critical Activity Being Crashed in CPM Network — Research Paper | ScholarLens