2014World BridgesRequires access

Construction Techniques for Steel-Concrete Composite Girder of Yingwuzhou Changjiang River Bridge in Wuhan

Fang Hua-bin

Open publisher page 0 citations

Abstract

The main bridge of Yingwuzhou Changjiang River Bridge in Wuhan is a three-tower four-span earth-anchored suspension bridge with span arrangement of(200+2×850+200)m.To counteract the bridge deck pavement damage,detaching and displacement,the main girder is designed as the steel-concrete composite girder structure covered with modified asphalt SMA pavement.To suit the new structural design,all the elements of the steel stiffening girder were prefabricated and assembled by long line method in the specialist steel structure workshop.The concrete deck slabs were also factory-made.The concrete deck slabs and the steel stiffening girder in the side spans were combined by using the two-phased combining construction technique,by which the elements in each section were combined first and then,the overall sections were combined.But for the concrete deck slabs and the steel stiffening girder in the intermediate spans,the concrete deck slabs in each section were temporarily fixed,and then connected by the wet concrete joints that were cast batch by batch.The engineering experience proves that the construction techniques used to the steel-concrete composite girder of the bridge exhibit sound effect.

About this research paper

What this paper is about

The main bridge of Yingwuzhou Changjiang River Bridge in Wuhan is a three-tower four-span earth-anchored suspension bridge with span arrangement of(200+2×850+200)m.To counteract the bridge deck pavement damage,detaching and displacement,the main girder is designed as the steel-concrete composite girder structure covered with modified asphalt SMA pavement.To suit the new structural design,all the elements of the steel stiffening girder were prefabricated and assembled by long line method in the specialist steel structure workshop.The concrete deck slabs were also factory-made.The concrete deck slabs and the steel stiffening girder in the side spans were combined by using the two-phased combining construction technique,by which the elements in each section were combined first and then,the overall sections were combined.But for the concrete deck slabs and the steel stiffening girder in the intermediate spans,the concrete deck slabs in each section were temporarily fixed,and then connected by the wet concrete joints that were cast batch by batch.The engineering experience proves that the construction techniques used to the steel-concrete composite girder of the bridge exhibit sound effect.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The main bridge of Yingwuzhou Changjiang River Bridge in Wuhan is a three-tower four-span earth-anchored suspension bridge with span arrangement of(200+2×850+200)m.To counteract the bridge deck pavement damage,detaching and displacement,the main girder is designed as the steel-concrete composite girder structure covered with modified asphalt SMA pavement.To suit the new structural design,all the elements of the steel stiffening girder were prefabricated and assembled by long line method in the specialist steel structure workshop.The concrete deck slabs were also factory-made.The concrete deck slabs and the steel stiffening girder in the side spans were combined by using the two-phased combining construction technique,by which the elements in each section were combined first and then,the overall sections were combined.But for the concrete deck slabs and the steel stiffening girder in the intermediate spans,the concrete deck slabs in each section were temporarily fixed,and then connected by the wet concrete joints that were cast batch by batch.The engineering experience proves that the construction techniques used to the steel-concrete composite girder of the bridge exhibit sound effect.

Key concepts: Deck, Girder, Stiffening, Structural engineering, Engineering, Bridge (graph theory), Precast concrete, Span (engineering)