Based on the engineering practice of the side slope excavation of Dayanchi section within the road for the construction traffic of Guandi Hydropower Station, the problems such as the selection of blasthole distance for presplit blasting, and the rock ridge, the levelness of the presplit face, lower hole-making rate of the auxiliary blastholes after the presplit blasting, the blasting network for prespliting and blasting zone and the angle change of the presplit hole etc. are analyzed; for which the specific solutions are put forward herein as well.

About this research paper

What this paper is about

Based on the engineering practice of the side slope excavation of Dayanchi section within the road for the construction traffic of Guandi Hydropower Station, the problems such as the selection of blasthole distance for presplit blasting, and the rock ridge, the levelness of the presplit face, lower hole-making rate of the auxiliary blastholes after the presplit blasting, the blasting network for prespliting and blasting zone and the angle change of the presplit hole etc. are analyzed; for which the specific solutions are put forward herein as well.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Based on the engineering practice of the side slope excavation of Dayanchi section within the road for the construction traffic of Guandi Hydropower Station, the problems such as the selection of blasthole distance for presplit blasting, and the rock ridge, the levelness of the presplit face, lower hole-making rate of the auxiliary blastholes after the presplit blasting, the blasting network for prespliting and blasting zone and the angle change of the presplit hole etc. are analyzed; for which the specific solutions are put forward herein as well.

Key concepts: Rock blasting, Hydropower, Ridge, Excavation, Geotechnical engineering, Engineering, Section (typography), Civil engineering