Earned time:a new optimal method of project schedule performance evaluation based on earned value

Guo Wen-jin

Open publisher page 0 citations

Abstract

The Earned Value Management methodology is a very important and systematic technique that evaluates project performance.This paper studies the disadvantages and limitations of traditional earned value method while evaluating the project Schedule Performance from the application point of view based on the introduction of the traditional earned value management method,and puts forward a performance evaluation method called Earned Time method.It corrects the deviation from traditional earned value method when evaluating the project Schedule Performance,and all the information needed comes form the traditional earned value management.

About this research paper

What this paper is about

The Earned Value Management methodology is a very important and systematic technique that evaluates project performance.This paper studies the disadvantages and limitations of traditional earned value method while evaluating the project Schedule Performance from the application point of view based on the introduction of the traditional earned value management method,and puts forward a performance evaluation method called Earned Time method.It corrects the deviation from traditional earned value method when evaluating the project Schedule Performance,and all the information needed comes form the traditional earned value management.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The Earned Value Management methodology is a very important and systematic technique that evaluates project performance.This paper studies the disadvantages and limitations of traditional earned value method while evaluating the project Schedule Performance from the application point of view based on the introduction of the traditional earned value management method,and puts forward a performance evaluation method called Earned Time method.It corrects the deviation from traditional earned value method when evaluating the project Schedule Performance,and all the information needed comes form the traditional earned value management.

Key concepts: Earned value management, Schedule, Value (mathematics), Computer science, Project management, Operations research, Point (geometry), Project portfolio management