Three-Dimensional Performance of an Over-Size Complex Excavation in Shanghai

Yibo Hou, W. D. Wang, J. H. Wang

Open publisher page 1 citations

Abstract

This paper presents an over-size complex excavation project. In order to control retaining wall lateral displacement and associated ground movement within specified limits, this project was constructed using the method of "central part by bottom-up method and peripheral part by top-down method". A comprehensive monitoring system was installed on this project to reduce risk and study the deformation behavior of such excavation. Wall displacement, ground surface movement and bottom heave were separately measured and analyzed during the excavation. Field observations indicate that the wall lateral displacement is correlated with the zoned excavation and floor slabs installation sequence. The ground surface settlement near the corner of the excavation is less than that near the center, which corresponds to those reported in the literature. The behaviors of the diaphragm wall and ground surface settlement are affected by the "creep effect".

About this research paper

What this paper is about

This paper presents an over-size complex excavation project. In order to control retaining wall lateral displacement and associated ground movement within specified limits, this project was constructed using the method of "central part by bottom-up method and peripheral part by top-down method". A comprehensive monitoring system was installed on this project to reduce risk and study the deformation behavior of such excavation. Wall displacement, ground surface movement and bottom heave were separately measured and analyzed during the excavation. Field observations indicate that the wall lateral displacement is correlated with the zoned excavation and floor slabs installation sequence. The ground surface settlement near the corner of the excavation is less than that near the center, which corresponds to those reported in the literature. The behaviors of the diaphragm wall and ground surface settlement are affected by the "creep effect".

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This paper presents an over-size complex excavation project. In order to control retaining wall lateral displacement and associated ground movement within specified limits, this project was constructed using the method of "central part by bottom-up method and peripheral part by top-down method". A comprehensive monitoring system was installed on this project to reduce risk and study the deformation behavior of such excavation. Wall displacement, ground surface movement and bottom heave were separately measured and analyzed during the excavation. Field observations indicate that the wall lateral displacement is correlated with the zoned excavation and floor slabs installation sequence. The ground surface settlement near the corner of the excavation is less than that near the center, which corresponds to those reported in the literature. The behaviors of the diaphragm wall and ground surface settlement are affected by the "creep effect".

Key concepts: Excavation, Ground movement, Geotechnical engineering, Settlement (finance), Displacement (psychology), Creep, Geology, Diaphragm (acoustics)