An integrated solution procedure for project staffing

Broos Maenhout, Mario Vanhoucke

Open publisher page 0 citations

Abstract

We study a strategic scheduling problem that integrates project scheduling and personnel staffing in order to determine how to staff and schedule single projects as best as possible. A decision is made on the best mix of resource types (regular workers, overtime and temporal workers) to carry out a single project. In this perspective, we want to determine the project schedule and deadline and the usage of the different resources in order to minimize the total cost.

About this research paper

What this paper is about

We study a strategic scheduling problem that integrates project scheduling and personnel staffing in order to determine how to staff and schedule single projects as best as possible. A decision is made on the best mix of resource types (regular workers, overtime and temporal workers) to carry out a single project. In this perspective, we want to determine the project schedule and deadline and the usage of the different resources in order to minimize the total cost.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

We study a strategic scheduling problem that integrates project scheduling and personnel staffing in order to determine how to staff and schedule single projects as best as possible. A decision is made on the best mix of resource types (regular workers, overtime and temporal workers) to carry out a single project. In this perspective, we want to determine the project schedule and deadline and the usage of the different resources in order to minimize the total cost.

Key concepts: Staffing, Schedule, Overtime, Scheduling (production processes), Computer science, Operations research, Operations management, Engineering