The State Highway 20 Mangere Motorway Extension project completed the link to Auckland International Airport and Manukau City and was the first significant design-build roading contract let in New Zealand by Transit NZ . The $40-million project involved the design and construction of 7 km of four lane highway, nine vehicular bridges and four footbridges, fill embankments up to 10 m high over soft ground and 3 main cuts typically 6 m up to 10m deep. In addition, some 200 m of tied back pre-cast walls and 800 m of cantilevered walls were required to retain areas within the designated urban motorway corridor. This paper outlines the geotechnical aspects of design and construction including the results of settlement monitoring using a horizontal profilometer, lateral load testing of piles, pile driving, earthworks control, the stability of cuts and an outline of pavement conditions.

About this research paper

What this paper is about

The State Highway 20 Mangere Motorway Extension project completed the link to Auckland International Airport and Manukau City and was the first significant design-build roading contract let in New Zealand by Transit NZ . The $40-million project involved the design and construction of 7 km of four lane highway, nine vehicular bridges and four footbridges, fill embankments up to 10 m high over soft ground and 3 main cuts typically 6 m up to 10m deep. In addition, some 200 m of tied back pre-cast walls and 800 m of cantilevered walls were required to retain areas within the designated urban motorway corridor. This paper outlines the geotechnical aspects of design and construction including the results of settlement monitoring using a horizontal profilometer, lateral load testing of piles, pile driving, earthworks control, the stability of cuts and an outline of pavement conditions.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The State Highway 20 Mangere Motorway Extension project completed the link to Auckland International Airport and Manukau City and was the first significant design-build roading contract let in New Zealand by Transit NZ . The $40-million project involved the design and construction of 7 km of four lane highway, nine vehicular bridges and four footbridges, fill embankments up to 10 m high over soft ground and 3 main cuts typically 6 m up to 10m deep. In addition, some 200 m of tied back pre-cast walls and 800 m of cantilevered walls were required to retain areas within the designated urban motorway corridor. This paper outlines the geotechnical aspects of design and construction including the results of settlement monitoring using a horizontal profilometer, lateral load testing of piles, pile driving, earthworks control, the stability of cuts and an outline of pavement conditions.

Key concepts: Earthworks, Engineering, Pile, Dirt, Geotechnical engineering, Civil engineering, Settlement (finance), Payment