Identifying Factors Leading to Cost Overrun in Construction Projects in Jordan

Ghanim A. Bekr

Open full text 22 citations

Abstract

The problem of cost overrun in construction industry is common worldwide and the construction industry in Jordan is no exception. The main objective of the study reported in this paper was to identify the causes of cost overrun in construction projects in Jordan. A comprehensive literature review from various sources was made to carry out the study. A questionnaire survey was conducted to find the causes of cost overrun related to clients, consultant, contractor, financial management, resources and external factors. More than 100 respondents participated in the survey. The survey identified 15 most important causes of cost overrun from a list of 49 different causes. The most important causes were: Schedule delay (time overrun), frequent design changes,  changes and additional works at owner request, mistakes and errors in design, inadequate planning and scheduling, inflation/ prices fluctuation, change in the scope of work (by owner), incomplete drawings/ detailed design at the time of tender, shortage of skilled  site workers, construction mistakes and defective works. In general the study revealed that all parties share responsibility for the cost overrun in the construction projects in Jordan. Keywords: Cost overrun, construction projects, importance index, causes of cost overrun, management Cite this Article Ghanim A. Bekr. Identifying Factors Leading to Cost Overrun in Construction Projects in Jordan . Journal of Construction Engineering, Technology and Management. 2015; 5(3): 25–33p.

About this research paper

What this paper is about

The problem of cost overrun in construction industry is common worldwide and the construction industry in Jordan is no exception. The main objective of the study reported in this paper was to identify the causes of cost overrun in construction projects in Jordan. A comprehensive literature review from various sources was made to carry out the study. A questionnaire survey was conducted to find the causes of cost overrun related to clients, consultant, contractor, financial management, resources and external factors. More than 100 respondents participated in the survey. The survey identified 15 most important causes of cost overrun from a list of 49 different causes. The most important causes were: Schedule delay (time overrun), frequent design changes,  changes and additional works at owner request, mistakes and errors in design, inadequate planning and scheduling, inflation/ prices fluctuation, change in the scope of work (by owner), incomplete drawings/ detailed design at the time of tender, shortage of skilled  site workers, construction mistakes and defective works. In general the study revealed that all parties share responsibility for the cost overrun in the construction projects in Jordan. Keywords: Cost overrun, construction projects, importance index, causes of cost overrun, management Cite this Article Ghanim A. Bekr. Identifying Factors Leading to Cost Overrun in Construction Projects in Jordan . Journal of Construction Engineering, Technology and Management. 2015; 5(3): 25–33p.

Why it matters

OpenAlex reports 22 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The problem of cost overrun in construction industry is common worldwide and the construction industry in Jordan is no exception. The main objective of the study reported in this paper was to identify the causes of cost overrun in construction projects in Jordan. A comprehensive literature review from various sources was made to carry out the study. A questionnaire survey was conducted to find the causes of cost overrun related to clients, consultant, contractor, financial management, resources and external factors. More than 100 respondents participated in the survey. The survey identified 15 most important causes of cost overrun from a list of 49 different causes. The most important causes were: Schedule delay (time overrun), frequent design changes,  changes and additional works at owner request, mistakes and errors in design, inadequate planning and scheduling, inflation/ prices fluctuation, change in the scope of work (by owner), incomplete drawings/ detailed design at the time of tender, shortage of skilled  site workers, construction mistakes and defective works. In general the study revealed that all parties share responsibility for the cost overrun in the construction projects in Jordan. Keywords: Cost overrun, construction projects, importance index, causes of cost overrun, management Cite this Article Ghanim A. Bekr. Identifying Factors Leading to Cost Overrun in Construction Projects in Jordan . Journal of Construction Engineering, Technology and Management. 2015; 5(3): 25–33p.

Key concepts: Cost overrun, Scope (computer science), Construction industry, Economic shortage, Operations management, Schedule, Change order, Business

Related papers

Back to paper searchBrowse research topicsOriginal source
Identifying Factors Leading to Cost Overrun in Construction Projects in Jordan — Research Paper | ScholarLens