Rolling the Dice on Late-season Sealcoating

Allan Heydorn

Open publisher page 0 citations

Abstract

This article describes a challenging sealcoating project in Atlanta, which involved sealing a 70,000 sq yd parking lot at the tail end of the season. Short work days and possible temperature and weather limitations required careful planning and scheduling. The property owner had to be willing to accept that the sealer could not be guaranteed if the project went past the cutoff date. The project was completed by working on smaller sections during the week when the property was open and then doing larger sections on weekends.

About this research paper

What this paper is about

This article describes a challenging sealcoating project in Atlanta, which involved sealing a 70,000 sq yd parking lot at the tail end of the season. Short work days and possible temperature and weather limitations required careful planning and scheduling. The property owner had to be willing to accept that the sealer could not be guaranteed if the project went past the cutoff date. The project was completed by working on smaller sections during the week when the property was open and then doing larger sections on weekends.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This article describes a challenging sealcoating project in Atlanta, which involved sealing a 70,000 sq yd parking lot at the tail end of the season. Short work days and possible temperature and weather limitations required careful planning and scheduling. The property owner had to be willing to accept that the sealer could not be guaranteed if the project went past the cutoff date. The project was completed by working on smaller sections during the week when the property was open and then doing larger sections on weekends.

Key concepts: Atlanta, Dice, Engineering, Parking lot, Work (physics), Property (philosophy), Operations management, Transport engineering

Related papers

Back to paper searchBrowse research topicsOriginal source
Rolling the Dice on Late-season Sealcoating — Research Paper | ScholarLens