Barge-Assisted Draft Reduction of Semi-Submersible Drilling Unit GSF Development Driller I for Tow-Out From Ingleside to Offshore Gulf of Mexico

Frank van Hoorn, Warren Weaver, James Brekke, S.D. Devoy

Open publisher page 0 citations

Abstract

Because of its DP thrusters, the free-floating draft of the semi-submersible drilling rig GSF Development Driller I was too deep for a safe tow-out from Ingleside, TX, to open waters. In order to reduce the semi’s draft, a large cargo barge was used to lift the rig 1.0 m (3.3 ft) and thus create a reasonable ground clearance. The barge was selected, based on dimension, ballast capability, deck strength, price, and availability. Eight support brackets were welded to the barge sides and strong diaphragms welded inside the four rig braces. Detailed time domain motion analyses were performed to study the behavior of the combined units during the tow and barge removal operation offshore. In April of 2006, during a favorable weather window, the combined units were successfully towed through the channels and once in deeper waters, the barge was ballasted down and pulled out from under the rig.

About this research paper

What this paper is about

Because of its DP thrusters, the free-floating draft of the semi-submersible drilling rig GSF Development Driller I was too deep for a safe tow-out from Ingleside, TX, to open waters. In order to reduce the semi’s draft, a large cargo barge was used to lift the rig 1.0 m (3.3 ft) and thus create a reasonable ground clearance. The barge was selected, based on dimension, ballast capability, deck strength, price, and availability. Eight support brackets were welded to the barge sides and strong diaphragms welded inside the four rig braces. Detailed time domain motion analyses were performed to study the behavior of the combined units during the tow and barge removal operation offshore. In April of 2006, during a favorable weather window, the combined units were successfully towed through the channels and once in deeper waters, the barge was ballasted down and pulled out from under the rig.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Because of its DP thrusters, the free-floating draft of the semi-submersible drilling rig GSF Development Driller I was too deep for a safe tow-out from Ingleside, TX, to open waters. In order to reduce the semi’s draft, a large cargo barge was used to lift the rig 1.0 m (3.3 ft) and thus create a reasonable ground clearance. The barge was selected, based on dimension, ballast capability, deck strength, price, and availability. Eight support brackets were welded to the barge sides and strong diaphragms welded inside the four rig braces. Detailed time domain motion analyses were performed to study the behavior of the combined units during the tow and barge removal operation offshore. In April of 2006, during a favorable weather window, the combined units were successfully towed through the channels and once in deeper waters, the barge was ballasted down and pulled out from under the rig.

Key concepts: BARGE, Marine engineering, Deck, Hull, Submarine pipeline, Ballast, Engineering, Deep water

Related papers

Back to paper searchBrowse research topicsOriginal source
Barge-Assisted Draft Reduction of Semi-Submersible Drilling Unit GSF Development Driller I for Tow-Out From Ingleside to Offshore Gulf of Mexico — Research Paper | ScholarLens