A step toward capacity planning at finite capacity in semiconductor manufacturing

Emna Mhiri, Mireille Jacomino, Fabien Mangione, Philippe Vialletelle, Guillaume Lepelletier

Open publisher page 4 citations

Abstract

Production planning in the Semiconductor Industry (SI) has emerged as the most complex process due to its process complexity, technological constraints and high-mix low-volume production characteristics. In this paper, we present two different production planning approaches, developed by STMicroelectronics and G-SCOP research laboratory, to better control the production in 300mm production line at Crolles. At first, a mixed integer program (MIP) is proposed that projects the production lot trajectories (start and end dates) for the remaining subsequent steps, taking into account finite production capacities. A heuristic is then proposed to simplify the problem of finite capacity by neglecting equipment capacity. This approach results in the development of an infinite capacity WIP projection engine that complies with lots due dates and takes into account cycle time variability.

About this research paper

What this paper is about

Production planning in the Semiconductor Industry (SI) has emerged as the most complex process due to its process complexity, technological constraints and high-mix low-volume production characteristics. In this paper, we present two different production planning approaches, developed by STMicroelectronics and G-SCOP research laboratory, to better control the production in 300mm production line at Crolles. At first, a mixed integer program (MIP) is proposed that projects the production lot trajectories (start and end dates) for the remaining subsequent steps, taking into account finite production capacities. A heuristic is then proposed to simplify the problem of finite capacity by neglecting equipment capacity. This approach results in the development of an infinite capacity WIP projection engine that complies with lots due dates and takes into account cycle time variability.

Why it matters

OpenAlex reports 4 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Production planning in the Semiconductor Industry (SI) has emerged as the most complex process due to its process complexity, technological constraints and high-mix low-volume production characteristics. In this paper, we present two different production planning approaches, developed by STMicroelectronics and G-SCOP research laboratory, to better control the production in 300mm production line at Crolles. At first, a mixed integer program (MIP) is proposed that projects the production lot trajectories (start and end dates) for the remaining subsequent steps, taking into account finite production capacities. A heuristic is then proposed to simplify the problem of finite capacity by neglecting equipment capacity. This approach results in the development of an infinite capacity WIP projection engine that complies with lots due dates and takes into account cycle time variability.

Key concepts: Capacity planning, Semiconductor device fabrication, Production (economics), Production line, Heuristic, Production planning, Process (computing), Computer science