FIRST BEAM RESULTS FOR A COLLIMATOR WITH IN-JAW BEAM POSITION MONITORS

Daniel Wollmann, O. Aberle, R. Aßmann, A. Bertarelli, C Boccard, Roderik Bruce, Florian Burkart, Marija Cauchi, Alessandro Dallocchio, D Deboy, M. Gąsior, R.M. Jones, Stefano Redaelli, Adriana Rossi, Gianluca Valentino

Open full text 7 citations

Abstract

With more than 100 collimators the LHC has the most complex collimation system ever installed in an accelerator. The beam-based setup time of the system was a nonnegligible factor during the commissioning of the LHC. In addition if the particle orbit at a collimator goes out of tolerance, this collimator needs to be setup again. To reduce the required setup time for the collimation system and to obtain the tight tolerances required for the LHC operation with small beta* and high beam energy, a new collimator design is being developed that integrates a beam position monitor (BPM) into the jaws of the collimator. A prototype of such a phase-II LHC collimator was installed in the SPS at CERN for the 2010 run. In this paper we present the first experimental results from the beam tests performed.

About this research paper

What this paper is about

With more than 100 collimators the LHC has the most complex collimation system ever installed in an accelerator. The beam-based setup time of the system was a nonnegligible factor during the commissioning of the LHC. In addition if the particle orbit at a collimator goes out of tolerance, this collimator needs to be setup again. To reduce the required setup time for the collimation system and to obtain the tight tolerances required for the LHC operation with small beta* and high beam energy, a new collimator design is being developed that integrates a beam position monitor (BPM) into the jaws of the collimator. A prototype of such a phase-II LHC collimator was installed in the SPS at CERN for the 2010 run. In this paper we present the first experimental results from the beam tests performed.

Why it matters

OpenAlex reports 7 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

With more than 100 collimators the LHC has the most complex collimation system ever installed in an accelerator. The beam-based setup time of the system was a nonnegligible factor during the commissioning of the LHC. In addition if the particle orbit at a collimator goes out of tolerance, this collimator needs to be setup again. To reduce the required setup time for the collimation system and to obtain the tight tolerances required for the LHC operation with small beta* and high beam energy, a new collimator design is being developed that integrates a beam position monitor (BPM) into the jaws of the collimator. A prototype of such a phase-II LHC collimator was installed in the SPS at CERN for the 2010 run. In this paper we present the first experimental results from the beam tests performed.

Key concepts: Collimator, Collimated light, Large Hadron Collider, Beam (structure), Optics, Physics, Nuclear physics, Laser

Related papers

Back to paper searchBrowse research topicsOriginal source
FIRST BEAM RESULTS FOR A COLLIMATOR WITH IN-JAW BEAM POSITION MONITORS — Research Paper | ScholarLens