Present status of NSLS-II design and construction

Sanjeev Sharma, Andrew Broadbent, L. Doom, M. Fallier, H. Hseuh, B. Kosciuk, V. Ravindranath, Timur Shaftan, А. И. Ситников, J. Skaritka

Open publisher page 0 citations

Abstract

National Synchrotron Light Source (NSLS-II) is a new 3 GeV, 500 mA, high-brightness synchrotron light source facility being built at the Brookhaven National Laboratory. Approved for construction in January 2009, the NSLS-II project is expected to be completed in June 2014. In this paper we discuss the present status of the mechanical design and construction of some major components of this facility, namely (i) conventional facilities, (ii) injector complex (iii) storage ring, (iv) RF system and (v) beamlines.

About this research paper

What this paper is about

National Synchrotron Light Source (NSLS-II) is a new 3 GeV, 500 mA, high-brightness synchrotron light source facility being built at the Brookhaven National Laboratory. Approved for construction in January 2009, the NSLS-II project is expected to be completed in June 2014. In this paper we discuss the present status of the mechanical design and construction of some major components of this facility, namely (i) conventional facilities, (ii) injector complex (iii) storage ring, (iv) RF system and (v) beamlines.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

National Synchrotron Light Source (NSLS-II) is a new 3 GeV, 500 mA, high-brightness synchrotron light source facility being built at the Brookhaven National Laboratory. Approved for construction in January 2009, the NSLS-II project is expected to be completed in June 2014. In this paper we discuss the present status of the mechanical design and construction of some major components of this facility, namely (i) conventional facilities, (ii) injector complex (iii) storage ring, (iv) RF system and (v) beamlines.

Key concepts: National laboratory, Storage ring, Synchrotron light source, Synchrotron, Physics, Particle accelerator, Linear particle accelerator, Brightness

Related papers

Back to paper searchBrowse research topicsOriginal source
Present status of NSLS-II design and construction — Research Paper | ScholarLens