Kaimai Tunnel project: Tunnel boring machine

Ken J Harrison, Robert Ec Taylor

Open publisher page 0 citations

Abstract

After extensive investigations at the planning stage of the project, it was decided to purchase a hardrock full-face tunnel-boring machine to excavate the tunnel in a single pass. A complex contract was arranged for both the supply of the machine and the supply and servicing of cutters for the duration of the project. Back-up equipment was designed and built in New Zealand by the Ministry of Works and Development. The machine was not successful in boring the blocky andesite prevailing at the western end of the tunnel The softer ignimbrites prevailing in the eastern half of the tunnel presented few problems to the machine and it bored approximately 5 km of tunnel from the eastern end. Operations from the eastern end of the tunnel were severely hampered in the early stages by major breakdowns. Assessment of the machine's performance revealed that, although not as spectacular as was envisaged, it met expectations and justified the use of this tunnelling method at Kaimai.

About this research paper

What this paper is about

After extensive investigations at the planning stage of the project, it was decided to purchase a hardrock full-face tunnel-boring machine to excavate the tunnel in a single pass. A complex contract was arranged for both the supply of the machine and the supply and servicing of cutters for the duration of the project. Back-up equipment was designed and built in New Zealand by the Ministry of Works and Development. The machine was not successful in boring the blocky andesite prevailing at the western end of the tunnel The softer ignimbrites prevailing in the eastern half of the tunnel presented few problems to the machine and it bored approximately 5 km of tunnel from the eastern end. Operations from the eastern end of the tunnel were severely hampered in the early stages by major breakdowns. Assessment of the machine's performance revealed that, although not as spectacular as was envisaged, it met expectations and justified the use of this tunnelling method at Kaimai.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

After extensive investigations at the planning stage of the project, it was decided to purchase a hardrock full-face tunnel-boring machine to excavate the tunnel in a single pass. A complex contract was arranged for both the supply of the machine and the supply and servicing of cutters for the duration of the project. Back-up equipment was designed and built in New Zealand by the Ministry of Works and Development. The machine was not successful in boring the blocky andesite prevailing at the western end of the tunnel The softer ignimbrites prevailing in the eastern half of the tunnel presented few problems to the machine and it bored approximately 5 km of tunnel from the eastern end. Operations from the eastern end of the tunnel were severely hampered in the early stages by major breakdowns. Assessment of the machine's performance revealed that, although not as spectacular as was envisaged, it met expectations and justified the use of this tunnelling method at Kaimai.

Key concepts: Tunnel boring machine, Christian ministry, Engineering, Mining engineering, Geology, Law, Mechanical engineering, Political science

Related papers

Back to paper searchBrowse research topicsOriginal source
Kaimai Tunnel project: Tunnel boring machine — Research Paper | ScholarLens