1993Proceedings of the Institution of Mechanical Engineers Part A Journal of Power and EnergyRequires access

The 900 MW Combined Cycle Gas Turbine Power Station Project at Killingholme

T E Chappell

Open publisher page 0 citations

Abstract

PowerGen's 900 MW combined cycle gas turbine (CCGT) power station at Killingholme achieved full load output over two months before the scheduled date for full commercial load and less than 34 months after the turnkey contract was placed. This paper reviews the development of PowerGen's first CCGT power station, discusses the reasons for the choice of this type of plant and examines early operating experience. The contract strategy, a technical description of the plant, the project programme and the environmental impact of the plant relative to a conventional coal-fired power station are also included.

About this research paper

What this paper is about

PowerGen's 900 MW combined cycle gas turbine (CCGT) power station at Killingholme achieved full load output over two months before the scheduled date for full commercial load and less than 34 months after the turnkey contract was placed. This paper reviews the development of PowerGen's first CCGT power station, discusses the reasons for the choice of this type of plant and examines early operating experience. The contract strategy, a technical description of the plant, the project programme and the environmental impact of the plant relative to a conventional coal-fired power station are also included.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

PowerGen's 900 MW combined cycle gas turbine (CCGT) power station at Killingholme achieved full load output over two months before the scheduled date for full commercial load and less than 34 months after the turnkey contract was placed. This paper reviews the development of PowerGen's first CCGT power station, discusses the reasons for the choice of this type of plant and examines early operating experience. The contract strategy, a technical description of the plant, the project programme and the environmental impact of the plant relative to a conventional coal-fired power station are also included.

Key concepts: Turnkey, Combined cycle, Power station, Gas turbines, Engineering, Turbine, Electricity generation, Coal

Related papers

Back to paper searchBrowse research topicsOriginal source
The 900 MW Combined Cycle Gas Turbine Power Station Project at Killingholme — Research Paper | ScholarLens