Analysis of Causes of Delay and Time Performance in Construction Projects
Pablo García González, Vicente A. González, Keith R. Molenaar, Francisco Orozco
Abstract
Pablo García González, Vicente A. González, Keith R. Molenaar, Francisco Orozco
Abstract
Activity delays are a common issue in the construction industry and can increase project schedules and costs. Recent research efforts have focused on the quantitative evaluation of delay impacts. The literature suggests that the construction industry is in need of additional research to systematically relate the causes of delays to their impacts. To overcome this limitation, this paper analyzes delay causes in activities that were not completed as scheduled. The paper contributes to a methodology to examine the qualitative (delay causes) and quantitative (time performance) dimensions of the delay issue. The paper proposes two indicators, as follows: (1) reason for noncompliance (RNC) as an indicator that characterizes scheduling failures, and (2) delay index (DI) as a time-performance indicator that describes the impacts of delay on critical and noncritical activities. The paper presents two building projects as case studies, with planning and subcontractors as the primary RNCs that have the greatest impact on time performance. Planning was the most harmful delay cause on time performance.
OpenAlex reports 141 citations for this work. Citation counts describe recorded attention and do not establish research quality.
A contribution statement is not available in the OpenAlex record.
Method details are not available in the OpenAlex metadata.
Findings are not separately available in the OpenAlex metadata.
Limitations are not available in the OpenAlex metadata.
Application details are not available in the OpenAlex metadata.
Activity delays are a common issue in the construction industry and can increase project schedules and costs. Recent research efforts have focused on the quantitative evaluation of delay impacts. The literature suggests that the construction industry is in need of additional research to systematically relate the causes of delays to their impacts. To overcome this limitation, this paper analyzes delay causes in activities that were not completed as scheduled. The paper contributes to a methodology to examine the qualitative (delay causes) and quantitative (time performance) dimensions of the delay issue. The paper proposes two indicators, as follows: (1) reason for noncompliance (RNC) as an indicator that characterizes scheduling failures, and (2) delay index (DI) as a time-performance indicator that describes the impacts of delay on critical and noncritical activities. The paper presents two building projects as case studies, with planning and subcontractors as the primary RNCs that have the greatest impact on time performance. Planning was the most harmful delay cause on time performance.
Key concepts: Scheduling (production processes), Computer science, Performance indicator, Risk analysis (engineering), Construction industry, Operations research, Reliability engineering, Operations management