1978Journal of the Air Pollution Control AssociationOpen access

Energy Requirements of a Limestone FGD System

Edward S. Rubin, Due G. Nguyen

Open full text 8 citations

Abstract

A computerized simulation model has been developed to compute energy requirements of a limestone slurry flue gas desulfurization (FGD) system as a function of FGD system design parameters, power plant characteristics, coal properties, and sulfur dioxide emission regulation. Results are illustrated for a "base case" plant of 500 MW, burning 3.5% sulfur coal, meeting the federal new source performance standard of 1.2 lb SO2/106 Btu. The flue gas is cleaned by an electrostatic precipitator followed by a limestone FGD system with a TCA scrubbing vessel and an optimized in-line steam reheater. The total FGD system energy requirement for this case was found to be 3.4% of the total energy input to the boiler. Sensitivity analyses were then performed in which the nominal values of ten system parameters were individually varied. This caused the total FGD system energy requirement to vary between 2.5 % and 6.1 % of the gross plant output for the range of parameters tested. The most sensitive parameters were found to be scrubbing slurry pH, which affects pumping requirements, and stack gas exit temperature, which affects reheat requirements. In all cases, FGD energy requirements were minimized when the SO2 emission standard was met by partially bypassing the scrubber. In light of the recent Clean Air Act Amendments this option may not be feasible in the future.

Open-access reader

About this research paper

What this paper is about

A computerized simulation model has been developed to compute energy requirements of a limestone slurry flue gas desulfurization (FGD) system as a function of FGD system design parameters, power plant characteristics, coal properties, and sulfur dioxide emission regulation. Results are illustrated for a "base case" plant of 500 MW, burning 3.5% sulfur coal, meeting the federal new source performance standard of 1.2 lb SO2/106 Btu. The flue gas is cleaned by an electrostatic precipitator followed by a limestone FGD system with a TCA scrubbing vessel and an optimized in-line steam reheater. The total FGD system energy requirement for this case was found to be 3.4% of the total energy input to the boiler. Sensitivity analyses were then performed in which the nominal values of ten system parameters were individually varied. This caused the total FGD system energy requirement to vary between 2.5 % and 6.1 % of the gross plant output for the range of parameters tested. The most sensitive parameters were found to be scrubbing slurry pH, which affects pumping requirements, and stack gas exit temperature, which affects reheat requirements. In all cases, FGD energy requirements were minimized when the SO2 emission standard was met by partially bypassing the scrubber. In light of the recent Clean Air Act Amendments this option may not be feasible in the future.

Why it matters

OpenAlex reports 8 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

A computerized simulation model has been developed to compute energy requirements of a limestone slurry flue gas desulfurization (FGD) system as a function of FGD system design parameters, power plant characteristics, coal properties, and sulfur dioxide emission regulation. Results are illustrated for a "base case" plant of 500 MW, burning 3.5% sulfur coal, meeting the federal new source performance standard of 1.2 lb SO2/106 Btu. The flue gas is cleaned by an electrostatic precipitator followed by a limestone FGD system with a TCA scrubbing vessel and an optimized in-line steam reheater. The total FGD system energy requirement for this case was found to be 3.4% of the total energy input to the boiler. Sensitivity analyses were then performed in which the nominal values of ten system parameters were individually varied. This caused the total FGD system energy requirement to vary between 2.5 % and 6.1 % of the gross plant output for the range of parameters tested. The most sensitive parameters were found to be scrubbing slurry pH, which affects pumping requirements, and stack gas exit temperature, which affects reheat requirements. In all cases, FGD energy requirements were minimized when the SO2 emission standard was met by partially bypassing the scrubber. In light of the recent Clean Air Act Amendments this option may not be feasible in the future.

Key concepts: Flue-gas desulfurization, Scrubber, Flue gas, Waste management, Electrostatic precipitator, Power station, Sulfur dioxide, Data scrubbing