2012•International Journal of Oil Gas and Coal TechnologyRequires access

An analysis of inaccuracy in pipeline construction cost estimation

Zhenhua Rui, Paul A. Metz, Gang Chen

Open publisher page 28 citations

Abstract

The aim of this paper is to investigate cost overrun of pipeline projects. A total of 412 pipeline projects between 1992 and 2008 have been collected, including material cost, labour cost, miscellaneous cost, right of way (ROW) cost, total cost, pipeline diameter, pipeline length, pipeline’s location, and year of completion. Statistical methods are used to identify the distribution of the cost overrun and the causes for overruns. The overall average cost overrun rates of pipeline material, labour, miscellaneous, ROW and total costs are 4.9%, 22.4%, –0.9%, 9.1% and 6.5% respectively. The cost estimation of pipeline cost components are biased except for total cost. In addition, the cost error of underestimated pipeline construction components is generally larger than that of overestimated pipeline construction components except total cost. Results of analysis show that pipeline size, capacity, diameter, length, location, and year of completion have different impacts on cost overrun of construction cost components.

About this research paper

What this paper is about

The aim of this paper is to investigate cost overrun of pipeline projects. A total of 412 pipeline projects between 1992 and 2008 have been collected, including material cost, labour cost, miscellaneous cost, right of way (ROW) cost, total cost, pipeline diameter, pipeline length, pipeline’s location, and year of completion. Statistical methods are used to identify the distribution of the cost overrun and the causes for overruns. The overall average cost overrun rates of pipeline material, labour, miscellaneous, ROW and total costs are 4.9%, 22.4%, –0.9%, 9.1% and 6.5% respectively. The cost estimation of pipeline cost components are biased except for total cost. In addition, the cost error of underestimated pipeline construction components is generally larger than that of overestimated pipeline construction components except total cost. Results of analysis show that pipeline size, capacity, diameter, length, location, and year of completion have different impacts on cost overrun of construction cost components.

Why it matters

OpenAlex reports 28 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

The aim of this paper is to investigate cost overrun of pipeline projects. A total of 412 pipeline projects between 1992 and 2008 have been collected, including material cost, labour cost, miscellaneous cost, right of way (ROW) cost, total cost, pipeline diameter, pipeline length, pipeline’s location, and year of completion. Statistical methods are used to identify the distribution of the cost overrun and the causes for overruns. The overall average cost overrun rates of pipeline material, labour, miscellaneous, ROW and total costs are 4.9%, 22.4%, –0.9%, 9.1% and 6.5% respectively. The cost estimation of pipeline cost components are biased except for total cost. In addition, the cost error of underestimated pipeline construction components is generally larger than that of overestimated pipeline construction components except total cost. Results of analysis show that pipeline size, capacity, diameter, length, location, and year of completion have different impacts on cost overrun of construction cost components.

Key concepts: Pipeline (software), Cost estimate, Total cost, Cost overrun, Cost analysis, Average cost, Engineering, Pipeline transport