Improving the flood control at a lower cost for a future Hydro-Québec hydroelectric facility on the Toulnustouc River, Canada

M Gaudette, G Bulota

Open publisher page 2 citations

Abstract

Prior to the construction of a new hydroelectric facility on the Toulnustouc River, Quebec, Canada, optimization was carried out on the dams and spillway design, resulting in a CAN$6 million reduction in the total project cost while improving flood control. This result was obtained using a new approach to the design of civil works, in which the dam and spillway were in complete interaction with one another. In this approach, the possibility of increasing the freeboard of the dams more than that usually required by Hydro-Québec criteria was allowed. The additional freeboard or reservoir volume is strictly assigned to flood control to reduce the maximum released discharge to existing downstream facilities. The raising of dam crests generates additional cost that is more than compensated for by a reduction in spillway capacity and cost.Key words: flood, control, cost, spillway, dam, optimization, security, freeboard.

About this research paper

What this paper is about

Prior to the construction of a new hydroelectric facility on the Toulnustouc River, Quebec, Canada, optimization was carried out on the dams and spillway design, resulting in a CAN$6 million reduction in the total project cost while improving flood control. This result was obtained using a new approach to the design of civil works, in which the dam and spillway were in complete interaction with one another. In this approach, the possibility of increasing the freeboard of the dams more than that usually required by Hydro-Québec criteria was allowed. The additional freeboard or reservoir volume is strictly assigned to flood control to reduce the maximum released discharge to existing downstream facilities. The raising of dam crests generates additional cost that is more than compensated for by a reduction in spillway capacity and cost.Key words: flood, control, cost, spillway, dam, optimization, security, freeboard.

Why it matters

OpenAlex reports 2 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Prior to the construction of a new hydroelectric facility on the Toulnustouc River, Quebec, Canada, optimization was carried out on the dams and spillway design, resulting in a CAN$6 million reduction in the total project cost while improving flood control. This result was obtained using a new approach to the design of civil works, in which the dam and spillway were in complete interaction with one another. In this approach, the possibility of increasing the freeboard of the dams more than that usually required by Hydro-Québec criteria was allowed. The additional freeboard or reservoir volume is strictly assigned to flood control to reduce the maximum released discharge to existing downstream facilities. The raising of dam crests generates additional cost that is more than compensated for by a reduction in spillway capacity and cost.Key words: flood, control, cost, spillway, dam, optimization, security, freeboard.

Key concepts: Spillway, Freeboard, Flood control, Hydroelectricity, Hydropower, Flood myth, Environmental science, Flooding (psychology)