The Use of Dynamically Positioned Units in Subsea Completions Offshore Brazil

J.R. Moreira

Open publisher page 0 citations

Abstract

ABSTRACT The intent of this paper is to document the major accomplishments achieved in the completion/workover of 28 wells using dynamically positioned (DP) units in the Campos Basin. The initial jobs were performed on wells equipped with conventional guideline trees and drilling bases and located in areas congested with subsea facilities. Minor changes of equipment design and operational procedures, permitted the successful performance of DP units on those conventional equipment. Based on the experience acquired from the forementioned jobs, guidelineless trees were designed and successfully installed in the Marlim field, at water depth beyond 700 m.

About this research paper

What this paper is about

ABSTRACT The intent of this paper is to document the major accomplishments achieved in the completion/workover of 28 wells using dynamically positioned (DP) units in the Campos Basin. The initial jobs were performed on wells equipped with conventional guideline trees and drilling bases and located in areas congested with subsea facilities. Minor changes of equipment design and operational procedures, permitted the successful performance of DP units on those conventional equipment. Based on the experience acquired from the forementioned jobs, guidelineless trees were designed and successfully installed in the Marlim field, at water depth beyond 700 m.

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

ABSTRACT The intent of this paper is to document the major accomplishments achieved in the completion/workover of 28 wells using dynamically positioned (DP) units in the Campos Basin. The initial jobs were performed on wells equipped with conventional guideline trees and drilling bases and located in areas congested with subsea facilities. Minor changes of equipment design and operational procedures, permitted the successful performance of DP units on those conventional equipment. Based on the experience acquired from the forementioned jobs, guidelineless trees were designed and successfully installed in the Marlim field, at water depth beyond 700 m.

Key concepts: Subsea, Workover, Submarine pipeline, Completion (oil and gas wells), Marine engineering, Petroleum engineering, Structural basin, Drilling