National Grid has been installing Numerical Busbar Protection (BBP) systems at its 400 kV, 275 kV and 132 kV double busbar substations for approximately ten years. This Paper investigates the design, operational and lifetime management experiences/challenges associated with moving to these solutions. The paper will consider these challenges under the following five categories: (1) Policy and application design (2) Operational experience to date (3) Contingency plans following unavailability (4) Spares holding and post commissioning support (5)Extendibility, Compatibility and Asset Life. (5 pages)

About this research paper

What this paper is about

National Grid has been installing Numerical Busbar Protection (BBP) systems at its 400 kV, 275 kV and 132 kV double busbar substations for approximately ten years. This Paper investigates the design, operational and lifetime management experiences/challenges associated with moving to these solutions. The paper will consider these challenges under the following five categories: (1) Policy and application design (2) Operational experience to date (3) Contingency plans following unavailability (4) Spares holding and post commissioning support (5)Extendibility, Compatibility and Asset Life. (5 pages)

Why it matters

A significance statement is not available in the OpenAlex record.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

National Grid has been installing Numerical Busbar Protection (BBP) systems at its 400 kV, 275 kV and 132 kV double busbar substations for approximately ten years. This Paper investigates the design, operational and lifetime management experiences/challenges associated with moving to these solutions. The paper will consider these challenges under the following five categories: (1) Policy and application design (2) Operational experience to date (3) Contingency plans following unavailability (4) Spares holding and post commissioning support (5)Extendibility, Compatibility and Asset Life. (5 pages)

Key concepts: Busbar, Unavailability, Installation, Engineering, Reliability engineering, Transmission system, Grid, Electric power transmission