Risk Analysis of Construction Schedule Based on PERT and MC Simulation

Jianwen Huang, Xingxia Wang

Open publisher page 17 citations

Abstract

In a construction project where duration truly equals money, the management of duration is critical, thus predicting the likelihood of duration may play a key role towards project success. On the basis of the researches of other scholars, this paper analyzed the traditional probability analysis method for duration risk in program evaluation and review technique(PERT). On basis of that it simulates the project' s duration and analyzes the risk of construction schedule by Monte Carlo simulation(MCS) method. Monte Carlo method was used to simulate the duration for each activity and the overall project to accurately determine the completion probability of the project under considering of the changeability and randomness of duration for each activity. The result shows that the MCS method is convenient, effective and efficient. It provides scientific basis for project decision-making and supports the decider powerfully.

About this research paper

What this paper is about

In a construction project where duration truly equals money, the management of duration is critical, thus predicting the likelihood of duration may play a key role towards project success. On the basis of the researches of other scholars, this paper analyzed the traditional probability analysis method for duration risk in program evaluation and review technique(PERT). On basis of that it simulates the project' s duration and analyzes the risk of construction schedule by Monte Carlo simulation(MCS) method. Monte Carlo method was used to simulate the duration for each activity and the overall project to accurately determine the completion probability of the project under considering of the changeability and randomness of duration for each activity. The result shows that the MCS method is convenient, effective and efficient. It provides scientific basis for project decision-making and supports the decider powerfully.

Why it matters

OpenAlex reports 17 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

In a construction project where duration truly equals money, the management of duration is critical, thus predicting the likelihood of duration may play a key role towards project success. On the basis of the researches of other scholars, this paper analyzed the traditional probability analysis method for duration risk in program evaluation and review technique(PERT). On basis of that it simulates the project' s duration and analyzes the risk of construction schedule by Monte Carlo simulation(MCS) method. Monte Carlo method was used to simulate the duration for each activity and the overall project to accurately determine the completion probability of the project under considering of the changeability and randomness of duration for each activity. The result shows that the MCS method is convenient, effective and efficient. It provides scientific basis for project decision-making and supports the decider powerfully.

Key concepts: Duration (music), Schedule, Monte Carlo method, Randomness, Computer science, Project management, Operations research, Basis (linear algebra)