Development of BWR Power Uprate Method Based on “Heat Balance Shift” Concept

Kazuaki Kitou, Masao Chaki, Motoo Aoyama, Kazuhiro Yoshikawa, Hiroshi Sasaki

Open publisher page 1 citations

Abstract

We have developed an innovative power uprate method for boiling water reactors (BWRs) that will increase thermal power by more than 5% without having to replace the high-pressure turbine. Reactor power uprate of nuclear power plants is an efficient plant operating method. Most BWR plants need to replace high-pressure turbines when thermal power is increased to over 5% because the main steam flow rate exceeds the inlet steam flow rate limit of the high-pressure turbine. A conventional power uprate method increases the feedwater and main steam flow rate in proportion to increase in thermal power. We examined a decrease in feedwater temperature instead of an increase in the feedwater and main steam flow rate. Since a decrease in feedwater temperature leads to a smaller main steam flow rate, a power uprate of over 5% can be achieved without replacing the high-pressure turbine. We call this power uprate method the “heat balance shift” method. In the present study, we evaluated the heat balance shift method to determine if it can increase electric power to a level higher than that of the conventional power uprate method without replacing the high-pressure turbine.

About this research paper

What this paper is about

We have developed an innovative power uprate method for boiling water reactors (BWRs) that will increase thermal power by more than 5% without having to replace the high-pressure turbine. Reactor power uprate of nuclear power plants is an efficient plant operating method. Most BWR plants need to replace high-pressure turbines when thermal power is increased to over 5% because the main steam flow rate exceeds the inlet steam flow rate limit of the high-pressure turbine. A conventional power uprate method increases the feedwater and main steam flow rate in proportion to increase in thermal power. We examined a decrease in feedwater temperature instead of an increase in the feedwater and main steam flow rate. Since a decrease in feedwater temperature leads to a smaller main steam flow rate, a power uprate of over 5% can be achieved without replacing the high-pressure turbine. We call this power uprate method the “heat balance shift” method. In the present study, we evaluated the heat balance shift method to determine if it can increase electric power to a level higher than that of the conventional power uprate method without replacing the high-pressure turbine.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

We have developed an innovative power uprate method for boiling water reactors (BWRs) that will increase thermal power by more than 5% without having to replace the high-pressure turbine. Reactor power uprate of nuclear power plants is an efficient plant operating method. Most BWR plants need to replace high-pressure turbines when thermal power is increased to over 5% because the main steam flow rate exceeds the inlet steam flow rate limit of the high-pressure turbine. A conventional power uprate method increases the feedwater and main steam flow rate in proportion to increase in thermal power. We examined a decrease in feedwater temperature instead of an increase in the feedwater and main steam flow rate. Since a decrease in feedwater temperature leads to a smaller main steam flow rate, a power uprate of over 5% can be achieved without replacing the high-pressure turbine. We call this power uprate method the “heat balance shift” method. In the present study, we evaluated the heat balance shift method to determine if it can increase electric power to a level higher than that of the conventional power uprate method without replacing the high-pressure turbine.

Key concepts: Boiler feedwater, Feedwater heater, Nuclear engineering, Turbine, Thermal power station, Boiler (water heating), Steam turbine, Volumetric flow rate