A costing system for the construction industry in Southern Africa

Evans Mushonga

Open full text 3 citations

Abstract

This research is based on the problem of allocating indirect overheads to construction projects in order to establish the performance of each project. Traditional costing (TC) systems and Activity-Based Costing (ABC) systems are both used for the allocation of overheads. \nBoth primary and secondary data were used in this research. Primary data was collected by means of two questionnaires, one addressed to construction companies and the other to consultants. The sample of respondents was obtained from the register of contractors and construction industry companies. The researcher sent the links to the Lime survey by email to all respondents. \nThe purpose of the literature review was to identify gaps and justify the need for this research. It considered existing findings by previous researchers. Primary data was therefore required to find answers specific to the problem of overheads allocation in the construction industry. According to the respondents, the use of TC systems produces distorted project cost results while ABC produces more accurate results when used in the construction industry. However, contractors had not adopted the ABC system but used TC systems despite their producing distorted project costs. \nIt is recommended that both TC and ABC systems be used in the construction industry since they complement each other. Contractors may have to adopt the ABC system to enhance their decision-making while continuing to use the TC systems for external reporting.

Open-access reader

About this research paper

What this paper is about

This research is based on the problem of allocating indirect overheads to construction projects in order to establish the performance of each project. Traditional costing (TC) systems and Activity-Based Costing (ABC) systems are both used for the allocation of overheads. \nBoth primary and secondary data were used in this research. Primary data was collected by means of two questionnaires, one addressed to construction companies and the other to consultants. The sample of respondents was obtained from the register of contractors and construction industry companies. The researcher sent the links to the Lime survey by email to all respondents. \nThe purpose of the literature review was to identify gaps and justify the need for this research. It considered existing findings by previous researchers. Primary data was therefore required to find answers specific to the problem of overheads allocation in the construction industry. According to the respondents, the use of TC systems produces distorted project cost results while ABC produces more accurate results when used in the construction industry. However, contractors had not adopted the ABC system but used TC systems despite their producing distorted project costs. \nIt is recommended that both TC and ABC systems be used in the construction industry since they complement each other. Contractors may have to adopt the ABC system to enhance their decision-making while continuing to use the TC systems for external reporting.

Why it matters

OpenAlex reports 3 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

This research is based on the problem of allocating indirect overheads to construction projects in order to establish the performance of each project. Traditional costing (TC) systems and Activity-Based Costing (ABC) systems are both used for the allocation of overheads. \nBoth primary and secondary data were used in this research. Primary data was collected by means of two questionnaires, one addressed to construction companies and the other to consultants. The sample of respondents was obtained from the register of contractors and construction industry companies. The researcher sent the links to the Lime survey by email to all respondents. \nThe purpose of the literature review was to identify gaps and justify the need for this research. It considered existing findings by previous researchers. Primary data was therefore required to find answers specific to the problem of overheads allocation in the construction industry. According to the respondents, the use of TC systems produces distorted project cost results while ABC produces more accurate results when used in the construction industry. However, contractors had not adopted the ABC system but used TC systems despite their producing distorted project costs. \nIt is recommended that both TC and ABC systems be used in the construction industry since they complement each other. Contractors may have to adopt the ABC system to enhance their decision-making while continuing to use the TC systems for external reporting.

Key concepts: Activity-based costing, Manufacturing engineering, Engineering, Business, Operations management, Construction engineering, Geography, Accounting