Hanford Waste Vitrification Plant process description and plant status

G.E. Stegen, L.D. Swenson

Open publisher page 1 citations

Abstract

Westinghouse Hanford Company in Richland, Washington, has integrating contractor responsibility for development, design, construction, and operation of the Hanford Waste Vitrification Plant (HWVP). The HWVP will be built for the US Department of Energy (DOE) to vitrify liquid high-level and transuranic (TRU) waste produced by defense activities at the Hanford Site. Start of construction is scheduled for 1992. Hot startup is scheduled for December 1999. Process design, project status, and requirements related to feed flexibility, interfaces with existing Hanford Site facilities, and other site-specific requirements are discussed in this paper.

About this research paper

What this paper is about

Westinghouse Hanford Company in Richland, Washington, has integrating contractor responsibility for development, design, construction, and operation of the Hanford Waste Vitrification Plant (HWVP). The HWVP will be built for the US Department of Energy (DOE) to vitrify liquid high-level and transuranic (TRU) waste produced by defense activities at the Hanford Site. Start of construction is scheduled for 1992. Hot startup is scheduled for December 1999. Process design, project status, and requirements related to feed flexibility, interfaces with existing Hanford Site facilities, and other site-specific requirements are discussed in this paper.

Why it matters

OpenAlex reports 1 citations for this work. Citation counts describe recorded attention and do not establish research quality.

Key contribution

A contribution statement is not available in the OpenAlex record.

Method / approach

Method details are not available in the OpenAlex metadata.

Main findings

Findings are not separately available in the OpenAlex metadata.

Limitations

Limitations are not available in the OpenAlex metadata.

Applications

Application details are not available in the OpenAlex metadata.

Available abstract

Westinghouse Hanford Company in Richland, Washington, has integrating contractor responsibility for development, design, construction, and operation of the Hanford Waste Vitrification Plant (HWVP). The HWVP will be built for the US Department of Energy (DOE) to vitrify liquid high-level and transuranic (TRU) waste produced by defense activities at the Hanford Site. Start of construction is scheduled for 1992. Hot startup is scheduled for December 1999. Process design, project status, and requirements related to feed flexibility, interfaces with existing Hanford Site facilities, and other site-specific requirements are discussed in this paper.

Key concepts: Hanford Site, Vitrification, Waste management, Radioactive waste, High-level waste, Engineering, Savannah River Site, Process (computing)